Construction in January continued in line with our expectations: The total concrete pour has now been totally effected, with over 90% of structural steel and 85% of mechanical installation completed. Installation of the SAG mill was completed in the month, and installation of its liner projected to start in February. The power plant is now over 80% complete, and the fuel depot 75% complete.

At the Boungou deposit, some 65% of the pre-stripping material has been extracted to date.