Natougou Media

 

April 2017 saw completion of the detailed design and engineering for the Boungou Mine. During the month, bulk earthworks for the processing plant were completed, in addition to the structural backfilling of the sub-foundations for the CIL tank, vertimill, crusher and SAG mill. Construction of the east water supply dam and the main dining hall has begun, while excavation of the water storage facility has finished. Earthworks for the living quarters, guardhouses and contractor camp are ongoing, and construction of the three bridges for the access road is near-complete.

Construction of the resettlement village is advancing well and has already reached the quarter mark.