Construction in December continued in line with our expectations: The total concrete pour has now been totally effected, with over 70% of structural steel and 55% of mechanical installation completed. Installation of the SAG mill is ongoing and expected to be completed in January. The power plant is now over three-quarters complete, and the fuel depot over 70% complete.

At month end, phase 1 of the tailings storage facility was almost fully complete. At the Boungou deposit, some 9.7 of the 18 million tonnes of pre-stripping material has now been extracted.