Construction in November continued in line with our expectations: Some 93% of the total concrete pour has now been effected, with almost 60% of structural steel and 33% of mechanical installation completed. Installation of the SAG mill is ongoing and expected to be completed in December. The power plant has reached the three-quarters completion stage, and the fuel depot is over halfway complete.

In the month, phase 1 of the tailings storage facility is almost fully complete. Ancillary and plant buildings are advancing well, with the majority scheduled for completion by year-end. 

At the Boungou deposit, some 8.3 of the 18 million tonnes of pre-stripping material has now been extracted.